Implementing elements of Last PlannerĀ® System in the Orchestra Wheel method
Cargando...
Archivos
Fecha
2021
Autores
Profesor/a GuĆa
Facultad/escuela
Idioma
es
TĆtulo de la revista
ISSN de la revista
TĆtulo del volumen
Editor
Universidad AndrƩs Bello
Nombre de Curso
Licencia CC
Licencia CC
Resumen
Due to the high costs and low level of productivity of high-rise building constructions, it
is necessary to plan the Tower Craneās stay on site. In a first instance and to establish a
baseline, a survey was conducted along with a Panel of Professional Experts to validate
how the Tower Crane works and the performance indicators mostly used in Chile. The
authors then developed a planning methodology, which has its origin in the āOrchestra
Wheelā method but incorporates elements from the Last PlannerĀ® System. The primary
aims were to achieve strategic planning and greater logistical detail to program the crane,
generating greater control of the fulfillment of tasks, adding stages for better planning,
and improving productivity. This new method was validated with an expert in the
"Orchestra Wheel" methodology and with a Panel of academic experts and researchers
who specialize in LPSāposing as future research, implementing this methodology in
different high-rise building construction projects.
Notas
ArtĆculo (Ingeniero Civil)
Palabras clave
Industria de la ConstrucciĆ³n, AdministraciĆ³n, ConstrucciĆ³n, PlanificaciĆ³n